Tlou Energy Limited provides update on construction of power transmission line for its plant at Lesedi in Botswana

2022-09-17 03:26:21 By : Ms. Cara Shih

The overall progress achieved is 11%, up from 8% reported last month, although the planned target was 17% indicating a slippage of 6%

Tlou Energy Limited provided an update on the construction of a power transmission line for its coal bed methane (CBM) extraction and power generation plant at Lesedi, west of Serowe in Botswana.

Tlou said overall progress achieved is currently 11% which is up from 8% reported last month, although the planned target was 17% indicating a slippage of 6%.

A 66 kilovolt (kV) transmission line and associated substations will connect the plant to the Botswana Power Corporation (BPC) grid at Serowe. The grid connection project is divided into two project parts; (i) the 66kV overhead transmission line, and (ii) the substation works at both ends of the line.

The 66kV transmission line construction contract between Tlou and Zismo Engineering was awarded on March 2, 2022, and commenced in April. The contract is expected to take approximately 15 months to complete, the company said.

The substation works tender has been awarded to OptiPower, a division of Murray & Roberts Ltd. The substation contract has not yet been signed and will be done once additional funding is in place, it added.

Tlou said a requirement to add pole savers (to provide added protection) to the wooden poles at the request of BPC was at the discretion of the engineer and had not been raised as an issue during the planning, design and procurement stages of the project. This will delay the planting of poles, it noted, and said procurement has also suffered delays with line hardware manufacturing resulting in delays to commence pole dressing and planting.

The slippage to date may be recovered in the coming months, the company noted. Procurement and other issues outside the company's control could delay the project further which will be advised in further updates if necessary, however, it said, at this time the transmission line section should remain close to the target completion date of mid-2023.

The Lesedi Power Project is located in Botswana's Central District, approximately 100 kilometres (km) from the existing electricity grid. The 66kV line being constructed will be capable of carrying up to 25MW of power. Initial electricity generated will be sold to Botswana Power Corporation, the national power utility under an agreed 10MW Power Purchase Agreement (PPA).

Tlou has been producing gas at its Lesedi 3P and Lesedi 4P production wells. The company has taken the decision to temporarily shut in the Lesedi 3P well as sufficient data exists from this well and there is no need to incur further production costs at this time. The well can be brought back into production as required. Gas production at Lesedi 4P is planned to continue.

In early trade on Tuesday, Tlou shares were 3.5% higher at 1.50p.

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Tlou Energy Ltd named herein, including the promotion by the Company of Tlou Energy Ltd in any Content on the Site, the Company receives from...

Tlou Energy Ltd (AIM:TLOU, ASX:TOU, BSE:TLOU) CEO and managing director Tony Gilby updates Proactive’s Andrew Scott on the construction of a power transmission line for its coal bed methane (CBM) extraction and power generation plant at Lesedi, west of Serowe in Botswana. The project is in...

Only registered members can use this feature.

Copyright © Proactive Group Holdings Inc, 2022

All Rights Reserved - Proactive Australia PTY LTD ACN:132787654 ABN:19132787654.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use.

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping us understand which sections of the website you find most interesting and useful. See our Cookie Policy for more information.

These cookies are used to deliver our website and content. Strictly necessary cookies relate to our hosting environment, and functional cookies are used to facilitate social logins, social sharing and rich-media content embeds.

Advertising Cookies collect information about your browsing habits such as the pages you visit and links you follow. These audience insights are used to make our website more relevant.

Performance Cookies collect anonymous information designed to help us improve the site and respond to the needs of our audiences. We use this information to make our site faster, more relevant and improve the navigation for all users.