NAWEC tours OMVG sites -

2022-06-03 22:14:41 By : Ms. Jenny Shu

For The Freedom of All We Labor Onward

The Gambia’s National Water And Electricity Company officials on Thursday toured OMVG project sites within greater Banjul and also briefed reporters about some ongoing developments.

Speaking to reporters in Brikama NAWEC’s Pierre Sylva, public relations officer  revealed  that OMVG Energy project involves a 1677km long 225kv interconnection line connecting the Gambia, Senegal, and Guinea Bissau, Guinea Conakry. In the Gambia there are 2 substations (Soma and Brikama), the substations are linked to the NAWEC) Network for the distribution of power.

He added that the Soma substation is running since October 2021 and Brikama is expected to be commissioned this month, March 2022.

He acknowledges   the challenges they are facing for not being able to meet the required capacity to supply electricity to the Gambian people especially the Greater Banjul Area.

“We are not folding our hands because we depend on the customers and that is why we have been working with the government and partners to make sure that we improve on the current capacity of electricity. This is an OMVG sub-station and OMVG is an organization where four countries of the sub-regions and East part of Africa have converged together to have this company for easy inter-connection of electricity,” he added.

Benedit Jarju, Quality and Standard Manager Distribution and Transmission Department said the OMVG project is between Gambia, Senegal, Guinea Conakry and Guinea Bissau, adding that Senegal has presently holds the capacity necessary for the supply of electricity to the Gambia.

“After completion this OMVG project will be interconnected with those transmission lines to bring energy from the OMVG. So far, the equipment is expected and about to be shipped in the Gambia and the installation work for the transformers will be starting in April and May,” he said.

He said currently everything is going smoothly and probably by the end of the year it will be completed and that is their expectation and hope that such a project will be a key sector.

He also said the project is a concern  and every work has challenges with the world  experiencing a lot of challenges including the COVID 19 and also the war between Ukraine and Russia.

“This is all the hindrance of the project despite the challenges we are mobilizing our resources as an international contractor. We are around over 17 countries and we are doing our best for the equipment to arrive in the Gambia on time. The major equipment to be delivered in the Gambia is power transformers including two 35KV and 33 KV transformers in addition this project has some transmission lines which will be connected to the current network,” he said.

By Adama Makasuba The ministry of health has announced that volunteer doctors have taken up responsibility in monitoring self-isolated coronavirus patients to ensure they are rapidly cured of the virus. “Volunteer doctors have taken it upon themselves to account for positive cases that are self-isolating at home by regularly calling and monitoring their conditions,” the […]

By Adama Makasuba The Gambian vice president Dr IsatouTouray has said people have taken her remarks about the country’s youth ‘out of context’. Dr Touray said during a distribution of food package for 84% Gambian households amid Covid-19 aimed at easing the burden of the virus impact, that she described the manual labour work as […]

Kebba Ansu Manneh Momodou M.C. Cham,, National Youth President of Gambia Democratic Congress (GDC) has authoritatively informed The Voice Newspaper that his party has finally agreed not to file election petition at the Supreme Court in Banjul to challenge the results of the 4th December, Presidential election. However, he was quick to reveals that the party […]

Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Enter your email address to subscribe to this Website and receive notifications of new posts by email.